21/01/2021 - Service Review - Asset Management & Car Parks ref: 436    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

.


21/01/2021 - Service Review - Communications & Marketing ref: 435    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

.


21/01/2021 - Service Review - Elections & Democratic Services ref: 434    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

.


21/01/2021 - Service Review - Law & Information Governance ref: 433    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

.


21/01/2021 - Service Review - Economic Growth & Tourism ref: 432    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

.


21/01/2021 - Service Review - Heritage & Culture ref: 431    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

.


21/01/2021 - Arkwood Developments Limited - Loan Agreement ref: 428    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Committee noted the exempt report regarding the Loan Agreement with Arkwood Developments Limited.

 

(Summary provided in accordance with Section 100C (2) of the Local Government Act 1972).

 


21/01/2021 - Arkwood Developments Limited - Loan Agreement ref: 427    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Business Manager – Law & Information Governance presented a report which updated Members in relation to the Council’s loan arrangements with Arkwood Developments Limited. It was reported that the terms of the loan agreement were now almost finalised, and once agreed in principle, there would be a final review in the context of new state subsidy rules before the agreement was finalised.

 

It was noted that the Director – Governance & Organisational Development and the Business Manager – Financial Services had previously been given delegated authority by the Committee to finalise and enter into the loan agreement on behalf of the Council.

 

AGREED (unanimously) that the report be noted.

 

Reason for Decision

 

To facilitate the progress of the housing development at Bowbridge Road by Arkwood Developments Limited, and future developments.


21/01/2021 - Policy & Finance Committee Revenue Budget 2021/22 ref: 425    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Business Manager – Financial Services presented a report which informed Members of the budget and scale of fees and charges for the areas falling under the remit of the Policy & Finance Committee for 2021/22.  Appendices A and B to the report summarised the budget proposed for the Committee for 2021/22 by service team and subjective level respectively. Appendix C to the report listed the reasons for increases or decreases of over £10,000 between the 2020/21 initial budget and proposed 2021/22 budget for services in Policy & Finance Committee. A schedule of proposed levels of fees and charges pertaining to the Committee were given at Appendix D. 

 

The Committee’s proposed 2021/22 budget was £490,000 more than its2020/21 initial budget; an increase of 10%. The £490,000 increase in the Committee’s proposed 2021/22 budget was comprised of a £709,000 increase in employee costs and a £26,000 increase in running cost, partially offset by a £245,000 increase in income.

 

AGREED (unanimously) that the following recommendations be made to Policy & Finance Committee at its meeting on 22 February 2021:

 

i.                    the 2021/22 base budget in Appendix A to the report, for inclusion in the overall council budget;

ii.                   and to Full Council on 9 March 2021 the 2021/22 fees & charges in Appendix D to the report.

 

Reason for Decision

 

To ensure that the budgets and fees and charges finally proposed for 2021/22 are recommended to the Policy & Finance Committee on 22 February 2021.


21/01/2021 - 2021/22 Housing Revenue Account (HRA) Budget and Rent Setting ref: 424    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Business Manager - Financial Services presented a report in relation to the Housing Revenue Account Budget and rent setting for 2021/22.  The report showed the actual outturn of the Housing Revenue Account for the year 2019/20; examined the proposed income and expenditure on the Housing Revenue Account for 2021/22 in accordance with Section 76 of the Local Government and Housing Act 1989; and provided indicative figures of income and expenditure for the financial years 2022/23 to 2024/25. The report also made recommendations to set rent levels and service charges for 2021/22 with effect from April 2021.

 

The setting of the Housing Revenue Account budget and the approval of rent levels would be presented to the Full Council Meeting in February 2021, which would allow the required time to notify tenants of proposed changes to rents in accordance with the legislation. 

 

AGREED (unanimously) to recommend to Full Council at its meeting on 9 February 2021:  

 

(a)    the HRA budget for 2021/22, as set out in Appendix A1 to the report;

 

(b)   an increase of 1.5% (CPI + 1%) in the 2021/22 rents of all properties in the HRA as at 31 March 2021;

 

(c)      an increase of 1.5% (CPI + 1%) in all 2021/22 service charges, except for the television (TV) licence costs payable by tenants of Gladstone House; and

 

(d)      that the TV licence costs payable by tenants of Gladstone House in 2021/22 remain at £0.21 per week.

 

Reason for Decision

 

To advise Members of the proposed HRA budget and changes in rent and service charge levels for 2021/22 and for these to be recommended to Council at its meeting on 9 February 2021.


21/01/2021 - Litigation Matter ref: 429    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Committee considered an exempt report regarding a litigation matter.

 

(Summary provided in accordance with Section 100C(2) of the Local Government Act

1972).


21/01/2021 - Business Resilience Programme ref: 426    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Business Manager – Economic Growth presented a report which outlined proposals for the delivery of a Business Resilience Programme focussing on key sectors identified in the Council’s Economic Growth Strategy. It was proposed that a fund of £300,000 be allocated to a series of programmes designed with sector delivery partners to enable business resilience and growth in identified sectors. This programme would be complimentary to the existing Retail High Street Diversification Fund created by the Council in November 2020 which was targeted at independent retailers.

 

The Programme would be delivered by the private sector and enabled through a procurement exercise to suppliers with specialisms in identified sectors. It was considered that this would assist in minimising the reliance on the public sector via solely grant provision and enable long term supported economic growth.

 

AGREED (unanimously) that the creation of £300,000 budget be approved, for the delivery of a Newark & Sherwood Business Resilience Programme running through 2021/22, funded through £100,000 use of the Additional Restrictions Grant and a one off contribution from the Council’s 2021/22 budget.

 

Reason for Decision

 

Businesses have endured a difficult year with the pandemic, and whilst survival has been the priority as we move into a national vaccination programme it is important for business and industry are able to adapt and build resilience. This approach will allow our local businesses in the identified key sectors of our economy, to have the necessary support for future economic growth.


21/01/2021 - Equality and Diversity Strategy 2021-23 ref: 421    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Director – Governance & Organisational Development presented a report concerning a light touch review of the Council’s Equality and Diversity Strategy. The Strategy had been due for review in 2020, however, given the challenges faced by the District, initially by the floods in February, followed by the outbreak of the pandemic, it was considered not appropriate to go out to consultation.  It was therefore proposed to undertake a light touch review to ensure that the Council continues to have an up to date document, and that a full review be undertaken once the results from the 2021 census were available.

 

AGREED             (unanimously) that the revised Equality & Diversity Strategy for 2021/23 be approved.

 

Reason for Decision

 

To ensure the Council can continue to fulfil its obligations under the Equality Act 2010 and the Public Sector Equality Duty.


21/01/2021 - Development of the Former Robin Hood Hotel ref: 430    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Committee considered an exempt report regarding the development of the former Robin Hood Hotel.

 

(Summary provided in accordance with Section 100C(2) of the Local Government Act

1972).


21/01/2021 - E-Newsletters ref: 422    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Assistant Director - Transformation & Communications presented a report which sought to replace the Council’s printed version of the Voice newsletter, to an E-newsletter format. Within this move, there was also a proposal to incorporate an alternative provision for tenants, where previously a quarterly printed publication was provided by Newark & Sherwood Homes. The proposal was not to return to a primary printed publication, either for residents or tenants, but to introduce an E-newsletter format which would equally be useable for both purposes and add a range of additional functionality.

 

The report outlined the benefits of moving to E-newsletters which included cost savings, interactive nature, issuing timely publications, as well meeting objectives within the Community Plan. Subject to approval, a procurement exercise would be undertaken to acquire the required software to produce E-newsletters and consultation would be required with tenants regarding the choices available and giving them the option to receive a paper version.  

 

As Chairman of the Homes & Communities Committee, Councillor T. Wendels confirmed that this Committee, at their meeting held on 18 January 2021, did support the recommendation to move to E-newsletters. However, concerns had been raised by the Committee that residents of the District should not miss out on information by not having paper copies. Councillor D Lloyd advised that certain publications would still be sent in paper form, such as Council Tax bills and rent change notifications and other information could be included with these. In addition, it was proposed that the implementation of the introduction of E-newsletters be reviewed in order to ensure residents and tenants were able to access appropriate information.

 

AGREED (unanimously) that:

 

(a)                    the proposed move to E-Newsletters to replace the current printed versions of the Voice and the development of an E-newsletter platform as set out in paragraph 4 of the report, be approved;

 

(b)                    the proposal to move to E-Newsletters, as an alternative provision for

Council tenants to replace the printed publications they previously received, be approved in principle, subject to the outcome of the consultation referred to in paragraph 5.2 of the report; and

 

(c)                     the Homes & Communities and Policy & Finance Committees both                           receive a review, when appropriate, on the implementation of both                             schemes.

 

Reason for Decision

 

To move forward with a modern digital way to communicate with our residents, which provides better value for money and best meets the needs of the resident and tenant.


21/01/2021 - General Fund, Housing Revenue Account (HRA) and Capital Projected Outturn Report to 31 March 2021 as at 30 November 2020 ref: 423    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 21/01/2021 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 21/01/2021

Decision:

The Business Manager – Financial Services presented a report which compared the Revised Budgets with the Projected Outturn forecast for the period ending 31 March 2021. The forecast was based on eight months performance on the Council’s revenue and capital budgets including the General Fund Revenue, Housing Revenue Account (HRA) and Capital Programme. The accounts showed a projected unfavourable variance against the revised budget of £0.942m on service budgets, with an overall unfavourable variance of £0.478m. Appendix A to the report detailed the variances in service areas and other budgets.

 

It was noted that the main reason for the projected unfavourable variance of £0.942m was because the Council was predicted to receive £1.719m less income from sales, fees and charges than budgeted for. However, it was estimated that the Council would be able to claim between £0.400m and £0.500m from the government in compensation for loss of income which would reduce the projected overall unfavourable variance.

 

The HRA budget showed a projected favourable variance against the revised budget of £2.042m. In respect of the Capital Programme, the additions and amendments which required approval were detailed in Appendix C to the report. If these variations were approved the revised budget would be reduced to £35.906m.

 

AGREED (unanimously) that:

 

(a)                           the General Fund projected unfavourable outturn variance of between £0.078m (unfavourable) and £(0.022)m (favourable) be noted;

 

(b)                        the Housing Revenue Account projected favourable outturn variance of £2.042m be noted;

 

(c)                the variations to the Capital Programme at Appendix C be approved;                and

 

(d)               the Capital Programme revised budget and financing of £35.906m be                         approved.

 

Reason for Decision

 

To update Members with the forecast outturn position for the 2020/21 financial year.


26/11/2020 - Flowserve Site Update ref: 392    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Director - Planning & Growth presented a report which provided an update relating to changes in ownership of the Flowserve site, the resulting likely impacts on the Flowserve Sports and Social Club’s occupation of sporting land on the site, and a proposition for the Council to enter into a financial relationship to provide a new landowner with an ongoing rental guarantee.

 

The landlord, CB Collier NK (SSC) Ltd, had informed the Council that, based on an appraisal of the financial standing of the Sports and Social club, it could only support retaining the Sports and Social Club (SSC) or other current sporting and community groups on the site if the Council were to step in to assist. Therefore, a request was made that the Council enter into an arrangement with the landlord to cover, via guarantee, up to £45,000 per annum in year 1, £55,000 per annum in year 2, and £75,000 per annum thereafter. The landlord confirmed that lease expectations were informed by advice from a firm of surveyors. It was considered that such rent levels were unsustainable and the Sports and Social Club, in conjunction with Newark Town Football Club, stated that an affordable lease was £10,000 per annum for the site.

 

It was considered disappointing that the Sports and Social Club and the landlord were unable to reach a mutually acceptable agreement. Ending the tenancy of the Sports and Social Club would lead to the loss of the sporting and community organisation facilities. However, the Council could act as honest broker for both parties to conclude a mutually acceptable arrangement, albeit that would require a significant reduction in lease expectations. The Council could also assist with work to find new accommodation for any club or organisation displaced if the lease was brought to an end and the Sports and Social Club or individual groups were required to vacate the site. It was noted that the site would remain as protected sports and recreational land irrespective of tenancy.

 

AGREED      (unanimously) that:

 

a)            CB Collier NK (SSC) Limited be informed that its proposal as detailed in paragraph 2.8 of the report is declined; and

 

b)            the Council offers to act as a broker between CB Collier NK (SSC) Limited and the Sports and Social Club to assist the parties in reaching a mutually acceptable lease arrangement, and if necessary assist the affected clubs and associations in finding alternative accommodation.

 

Reason for Decision

 

To update Members on recent developments and to make clear the Council’s position.

 


26/11/2020 - Newark Towns Fund ref: 399    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020


26/11/2020 - Newark Towns Fund ref: 390    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Director - Planning & Growth presented a report which provided an update on the Newark Town Investment Plan (TIP) and sought approval for the appropriate budget to progress with feasibility work for the Council owned Great North Road Gateway Site.

 

In accordance with the Towns Fund guidance, the Newark TIP was formally submitted to the Government on 31 July 2020 which was the deadline for the first cohort. To date seven places within this first cohort had been announced. Following the submission of the TIP a number of qualifications had been provided to the Government who have been assessing the proposals. The Government were still to announce if the TIP was to be supported but it was hoped that the Council would secure significant investment.

 

The Director – Planning & Growth referred to the report considered by the Economic Development Committee at their meeting held on 18 November which provided an update on a number of TIP projects. The report to this Committee focused on the Great North Road ‘Gateway Site’ which was in the Council’s ownership.

 

In relation to the existing livestock market it was noted that a third party had confirmed they wished to progress with a new livestock market but not at the current site. The current site remained vacant and redundant. In the interests of reducing holding costs for the Council and preparing the site for redevelopment it was recommended that funds were made available to tender for the demolition and secure holding of the existing cattle market site.

 

In relation to the lorry park, if the Council were to consider any relocation, it will be necessary for feasibility work to be undertaken in order to understand the acceptability and costs of its relocation. This feasibility work would need to be progressed alongside feasibility work for the technical ability and capacity of the Gateway Site to accommodate a range of aspirations including the International Air and Space Training Institute. The projected costs for demolition of the existing cattle market and the feasibility works were detailed in a separate exempt report.

 

AGREED      (unanimously) that:

 

a)            the ongoing negotiations with Government to secure a capital contribution from the Towns Fund of up to £25mbe noted;

 

b)            the allocation of budget outlined in the exempt report to secure the demolition and secure holding of the existing Cattle Market site be approved;

 

c)             the allocation of budget outlined in the exempt report to undertake feasibility work on the relocation of the Cattle Market and Lorry Park to Newark Showground or other identified site(s) be approved; and

 

d)            the allocation of budget outlined in the exempt report to undertake feasibility work on developing the Newark Gateway Site (the exiting Cattle Market and lorry park), including the delivery of the Newark Town Investment Plan aspirations be approved.

 

Reason for Decision

 

To continue the development the Newark Towns Strategy and Investment Plan.


26/11/2020 - Infrastructure Funding Statement ref: 391    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Business Manager - Planning Policy & Infrastructure presented a report which provided the Committee with the first iteration of the Council’s Infrastructure Funding Statement (IFS). This comprised of a report relating to the previous financial year on Community Infrastructure Ley (CIL) and Section 106 planning obligations, and a report on the infrastructure projects or types of infrastructure that the Council intended to fund wholly or partly by the levy, excluding the neighbourhood portion. It was noted that the IFS was a requirement of amended CIL legislation.

 

AGREED      (unanimously) that the Infrastructure Funding Statement, attached as an Appendix to the report, be approved for publication before the end of the calendar year.

 

Reason for Decision

 

To ensure that the District Council was operating in accordance with the requirements of the Community Infrastructure Regulations.


26/11/2020 - Grounds Maintenance of HRA Land ref: 387    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Director - Housing, Health & Wellbeing presented a report which set out a business case for Newark & Sherwood District Council’s Street Scene Service to deliver the grounds maintenance of Housing Revenue Account (HRA) or housing service land rather than contracting the service to a third party. The Director - Housing, Health & Wellbeing reported that the both the Homes & Communities and Leisure & Environment  Committees had supported the proposal to bring the existing contract to an end and bring the service in-house and were recommending approval to the Policy & Finance Committee.

 

The report detailed the review of the current service which had been subject to consultation through a tenant survey. Three options were set out in the report: A- no change to the current contract specification; B - changes to the current specification to deliver a higher specification service in line with tenant requests for improvement; and C - adaptation of the current specification to deliver a higher specification service. In respect of staffing all three options required an increase in the current Street Scene staffing levels. The existing contractor, ID Verde, were likely to have a number of staff working on the contract for the whole time, therefore TUPE regulations would apply if the contract was to be awarded to the District Council.

 

The report set out the estimated 2021/22 revenue costs of extending the current contract and of the three options proposed if the Council were to deliver the service in-house. General fund revenue costs were for the purchase of small grounds maintenance equipment with the purchase of vehicles and larger equipment would be capital expenditure.

 

AGREED      (unanimously) that:

 

(a)          the termination of the existing grounds maintenance contract be approved with the grounds maintenance service for the Housing Revenue Account to be in sourced and provided through Newark & Sherwood District Council’s  Street Scene; and

 

(b)          a one off revenue cost to the General Fund of £14,420 (to be funded from reserves) and a capital outlay of £133,600 (funded by borrowing) for Option A be approved.

 

Reason for Decision

 

Providing greater efficiencies through the synergies between the existing in-house provision and the requirements for maintaining HRA land; to improve accountability to tenants on the quality and responsive of the grounds maintenance and street scene, giving a consistent service to tenants; and to strengthen our in-house team and secure additional contracts that enable the Council to improve and maintain a ‘Cleaner Safer Greener’ District.

 

 


26/11/2020 - Newark Castle Electrical Upgrade and Fire Alarm Installation ref: 394    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Business Manager – Heritage, Culture & Visitors presented a report advising Members of health and safety works identified at Newark Castle and requesting that budget was allocated from the Change Management reserve to complete this work in-year.

 

In 2019, a health and safety review of Newark Castle was undertaken which included a refresh of the site’s fire risk assessment and assessment of the wiring and electrical systems. Following the review, EP Consultants were appointed and commenced work in January 2020 to design a fire alarm system, electrics and emergency lighting system as identified in the review. Work was put on hold due to the pandemic, however the works were now urgently required to ensure the Castle could deliver events during 2021.

 

AGREED      (unanimously) that a capital budget be created in 2020/21 for £85,000, financed from the Change Management and Management Carry Forwards Reserve for the required Newark Castle works.

 

Reason for Decision

 

To complete works urgently as identified in the health and safety risk review. 


26/11/2020 - Urgency Item - Next Steps Accommodation Programme ref: 398    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020


26/11/2020 - Ollerton Local Housing Office - Refurbishment and Re-Purpose ref: 395    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Business Manager – Customer Services presented a report which sought approval to refurbish the Ollerton local office and refocus the purpose for it to become a multi-use facility. It was reported that it was not possible with the current layouts, to make either the Town Hall or the Council local hosing office, Covid-19 secure. Consequently customer facing services could not be delivered from those locations. It was therefore being proposed to refurbish the local housing office to provide space for Customer Services to provide all Council services including a digital area for customers to self-serve, thereby supporting the Council’s digital agenda. 

 

Discussions would also take place with other potential partners regarding the possibility of delivering services from this location. However, it was noted that space at this location was limited. The proposed refurbishment was seen as an interim solution whilst the regeneration of Ollerton town centre and the development of a public sector hub came to fruition. Current estimates for costs of the refurbishment were £50,000. The Business Manager – Customer Services reported that the proposal had been supported by the Homes & Communities Committee at their meeting held on23 November 2020.

 

AGREED      (unanimously) that the proposal to refurbish and re-purpose the local housing office in Ollerton, as detailed in the report be approved and the project be added to the HRA Capital Programme for 2020/21.

 

Reason for Decision

 

To enable the Council to deliver a face-to-face service to its customers in the Sherwood area and to have a fit for purpose office facility for officers to access when working in that area of the District.


26/11/2020 - Revised Customer Feedback Policy ref: 389    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Business Manager – Customer Services presented a report which sought approval for a revised Customer Feedback Policy. The Policy had been revised following the re-integration of housing services back into the Council from Newark and Sherwood Homes. The Policy had also been updated to incorporate the latest best practice from the Local Government and Social Care Ombudsman and the Housing Ombudsman to ensure it was compliant with the relevant codes of practice. It was reported that the Homes & Communities had recommended approval of the revised Policy. 

 

AGREED      (unanimously) that the revised Customer Feedback Policy be approved.

 

Reason for Decision

 

To ensure the Customer Feedback Policy is fit for purpose and adheres to both of the Ombudsman’s Code of Practices.  

 


26/11/2020 - Partnership for the East Midlands Building Consultancy ref: 388    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Director - Planning & Growth presented a report which provided an update on the outcomes of the Practitioner Led Service Review of the service which included the financial position for the East Midlands Building Consultancy (EMBC) and the Council, and the recommended next steps for the partnership and extension of the contract.

 

The service review was undertaken by Capita with the aim to analyse the current service provision and provide suggested solutions to improve the service in the short, medium and long terms. Three service improvements were suggested: option 1 – business as usual with service improvements; option 2 – joint ventures – larger informal partnership with other councils / partners; and option 3 – a joint authority wholly owned trading company.

 

The outcome of the review was option 1 - to continue with the existing partnership with South Kesteven District Council and Rushcliffe Borough Council with service improvements which would still allow for services to be provided to other local authorities on a consultancy basis rather than a formal partnership.

 

The report provided full details of the EMBC financial position which took into account the impact of Covid-19 on income and furloughing staff. Based on income to date the forecast position was that there could be a trading deficit of £8,256 and general fund contribution of £74,167 per partner.If accurate this would comprise an increase of £474 on the budgeted contribution per partner. 

 

AGREED      (unanimously) that:

 

a)            the existing contract with East Midlands Building Consultancy for Building Control Services in partnership with Rushcliffe Borough Council and South Kesteven District Council be extended until April 2023, subject to annual review; and

 

b)            the financial position of the East Midlands Building Consultancy be noted.

 

Reason for Decision

 

To provide a sustainable Building Control service in partnership with neighbouring authorities.

 


26/11/2020 - Quarter 2 (Q2) 2020/21 Performance Report ref: 396    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Assistant Director – Transformation & Communications presented a report which gave Members an overview of Quarter 2 performance against the objectives and actions within the Council’s refreshed Community Plan for 2019-2023 and a range of other performance information. The report provided a commentary on progress against the eleven Community Plan objectives, reported on customer contacts, customer feedback and details of staff sickness absence rates.

 

AGREED      (unanimously) that the report be noted.

 

Reason for Decision

 

To enable the Committee to proactively monitor and manage achievement of the Council’s objectives as set out in the Community Plan.

 


26/11/2020 - Covid-19 Revenue Support - Business Grants and Assurance, Council Tax Hardship Fund, Test and Trace Support Payments ref: 397    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Business Manager – Revenues & Benefits presented a report which provided Members with an update on the administration of a number of revenue support schemes including the business rate grant fund(s), the council tax hardship fund and test and trace support payments, all in light of the Covid-19 pandemic. The report also provided assurances over the pre and post checks that had been conducted so far.

 

AGREED      (unanimously) that:

 

(a)          the progress made with the administration of the Business Grant Schemes, Council Tax Hardship Fund and the Test and Trace Support Payments be noted; and

 

(b)          the pre and post assurance checks conducted so far be noted.

 

Reason for Decision

 

To provide Members with an update on the administration of a number of Covid-19 revenue support schemes and to provide assurance of those schemes.

 


26/11/2020 - Development of the Former Robin Hood Hotel ref: 400    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020


26/11/2020 - General Fund, Housing Revenue Account (HRA) and Capital Projected Outturn Report to 31 March 2021 as at 30 September 2020 ref: 393    Recommendations Approved

Decision Maker: Policy & Finance Committee

Made at meeting: 26/11/2020 - Policy & Finance Committee

Decision published: 29/03/2021

Effective from: 26/11/2020

Decision:

The Deputy Chief Executive, Director - Resources and Section 151 Officer presented a report which compared the Revised Budgets with the Projected Outturn forecast for the period ending 31 March 2021. The forecast was based on six months performance on the Council’s revenue and capital budgets including the General Fund Revenue, Housing Revenue Account (HRA) and Capital Programme. The accounts showed a projected unfavourable variance of against the revised budget of £0.953mon service budgets, with an overall unfavourable variance of £1.094m. Appendix A to the report detailed the variances in service areas and other budgets. 

 

It was noted that the main reason for the projected unfavourable variance of £0.953m was because of the predicted £1.643mless in fee income than budgeted for. However it was estimated that the Council would be able to claim between £0.300m and £0.500m from the Government in compensation for such loss of income from fees and charges. Appendix B to the report showed the areas that were predicting falls in income. It was also noted that the Nottinghamshire Business Rates Pool may return some funding for the Council in 2020/21. 

 

The HRA budget showed a projected favourable variance against the approved budget of £1.955m. In respect of the Capital Programme, the additions and amendments which required approval were detailed in Appendix C to the report. If these variations were approved the revised budget would be reduced to £56.998m.

 

AGREED      (unanimously) that:

 

a)            the General Fund projected unfavourable outturn variance of between £0.594m and £0.794m be noted;

 

b)            the Housing Revenue Account projected favourable outturn variance of £1.955m be noted;

 

c)             the variations to the Capital Programme at Appendix C to the report be approved; and

 

d)            the Capital Programme projected outturn and financing of £56.505m be noted.

 

Reason for the Decision

 

To update Members with the forecast outturn position for the 2020/21 financial year.