Issue - decisions

Jubilee Bridge Refurbishment Options

22/02/2023 - Funding Requirement for Jubilee Bridge Maintenance Costs (Key Decision)

Members are requested to approve option three for the reasons cited within the contents of this report. This is recommended that given the prolonged lifespan of the more durable materials and the lower repair costs. On approval of option three an estimated budget cost of £333,499.67 + Vat will then be added to the capital programme.

 

AGREED That Cabinet:

 

a)      approve repair option 3 to Upgrade the existing approach ramp with steel trays infilled with tarmacadam / hot rolled stone chippings to match the existing subject to approval by a structural engineer; and

 

b)      approve an estimated budget cost of £333,499.67 + Vat will then be added to the capital programme.