Jubilee Bridge Refurbishment

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

That Cabinet approve:

 

a)        option 3 as set out in the report, to continue to carry out annual safety inspections and the required remedial maintenance, until the next Principal Bridge Inspection is due in 2030 at a cost of up to £XXXXXX; and

 

b)       the Capital budget be reduced from £333,500 to £XXXXXX which will decommit £XXXXXX from the Asset Maintenance Reserve.

 

Reason for Decision:

 

To ensure the bridge remains in a safe condition, the most viable option to the Council, based on the current condition of the bridge.

 

Options Considered:

 

Option 1 - Pay Commuted sum to Nottinghamshire County Council to have the bridge adopted and to remove future liability of the bridge from NSDC.

 

Option 2 - To retain the bridge and to carry out a bridge major refurbishment.

 

Option 3 - Continue to carry out annual safety inspections, remedial and recommended maintenance, until the next Principal Bridge Inspection is due, 2030.

 

Option 4 - Close the bridge and decommission 

Publication date: 22/01/2025

Date of decision: 21/01/2025

Decided at meeting: 21/01/2025 - Cabinet

Effective from: 28/01/2025