Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
That Cabinet:
a) agree to utilise the capital grant of £61,356 awarded to progress the implementation of LED lighting upgrades and new pool covers at Newark Sports & Fitness Centre, and
b) add a budget of up to £71,356 to the Council’s Capital programme, financed by the SPSF grant of £61,356 and up to £10,000 from Repairs & Renewals in order that the works can proceed.
Publication date: 06/06/2024
Date of decision: 04/06/2024
Decided at meeting: 04/06/2024 - Cabinet
Effective from: 12/06/2024
Accompanying Documents: