Southwell Leisure Centre Works (Key Decision)

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

That Cabinet:

 

(a)     approves an additional transfer of £161,800 funded from the Change Management Reserve, giving a total Capital budget of £740,000 to carry out the essential works to the dry side facility as set out in this report;

(b)     note that whilst every effort will be made to phase the works to keep the Leisure Centre operational at all times, there is a possibility that the Leisure Centre may have to close for a period of time in order for the works to be carried out safely, effectively and efficiently; and

(c)     note that in the event of closure, Active4Today will endeavour to accommodate customers at the Newark and Dukeries facilities, and that the Leisure Centre members affected will have their direct debits reduced to a nil payment where appropriate.

Report author: Mark Eyre

Publication date: 01/11/2023

Date of decision: 31/10/2023

Decided at meeting: 31/10/2023 - Cabinet

Effective from: 07/11/2023